• Construction, installations of outdoor switchgear, panel installation and wiring the control panel and primary commissioning of a 33/11kV substation at Zambia sugar-Nakambala including Control Building and other associated civil works and construction,
• Installation and primary commissioning of 2 x 5MVA pump stations and associated civil Works.
SUBCONTRACTOR

Client : ABB South Africa.

Location : Zambia sugar-Nakambala

Area :

Finished On :